What is the minimum thickness of concrete slabs and beam?

This is the minimum thickness of Concrete structures to satisfy Code requirements, if less numbers of this table are used , deflection must be checked.




Item

Min thick.

Simple

 

Con. One end

Cont. 2 ends

Cantilever

Notes

Beams and

Ribbed slab

 

L/16

L/20

L/18

L/22

L/21

L/26

L/8

L/10

High tensile steel

Normal mild steel

One Way Solid Slab

8cm static load

12cm dynamic load

L/20

L/25

L/24

L/30

L/28

L/35

L/10

L/12

High tensile steel

Normal mild steel

Tow Way Solid Slab

8cm static load

12cm dynamic load

a/35

a/40

a/45

 

A=short direction

Flat slab

150mm

 

No drop panel

With drop panel

 

L=(L1+L2)/2

External panel

L/32

L/36

 

Internal Panel

L/36

L/40

 

               


Minimum and maximum reinforcement in concrete structures

Comments

Popular posts from this blog

Differences between development length, anchorage length and splice length

  1-Development length Ld It is the minimum length of a reinforcing bar that must be embedded or "developed" in concrete to ensure that the bar can achieve its full strength in tension or compression. 2-Anchorage length La The distance that the reinforcement extends from the point where the bars are no longer required to resist moments 3-Splice length LS The distance require to transfer the force from bar to another one to upload full presentation please download this  https://drive.google.com/file/d/1layyDvTlJOLzo3jfoW4K5O5UEkgoEzgN/view?usp=sharing

KEYSTONE RETAINING WALL

 Introduction:- Keystone is a mechanical stabilized earth wall MSEW which used to retain soil from one side, it's less cost than concrete walls. Material  1-Keystone Blocks 2-Fiberglass Pins 3-Geo-grids 4- Back-filling Material 5-Concrete pad  Different type of Geogrid:  TT045 can carry load till 45KN/m. TT060 can carry load till. 60KN/m. TT090 can carry load till 90KN/m.  TT120 can carry load till 120KN/m.  TT160 can carry load till. 160KN/m. Method Statement  1) Place HDPE Geogrids on top of the compacted soil. HDPE Geogrids are installed from the front on top of the fiber glass pins (which penetrates the grid) and from to back, Geogrids are fixed horizontally using a steel bars.  2) Lay down the precast concrete units on top of a PC foundation at a level that is a Minimum of 5% from the wall height and reach 10% (buried height) to prevent any lateral movement .  3) Put the layers of Geotextile.  4) Backfilling using fine gravel b...

FIDIC Constructions 2017- some important clauses

 this is some of  FIDIC clauses  and actions required by contractor and employee Clause no Clause Action by Action 1.9 Delayed drawings Contractor - Give notice to engineer -EOT+ cost+ profit 1.13 Compliance with laws Employer To give all required permits and licenses     Contractor For delayed permits : EOT+ cost+ profit 1.6 Contract agreement Employer Within 35 day after letter of acceptance 2.1 Right of access to the site Employer       Contractor If delayed EOT+ cost+ profit 2.4 Employers financial arrangement employer Give notice to the contractor when 1-variation >10% or sum of all variations >30% 2- doesn’t receive p...