Welding of Structural Steel .
1 Pre-weld Inspection .
1 The surface to be welded and the filler material to be used shall be subject to inspection by quality control personnel before welding is performed. .

2 Method and Type
 .1 All welding indicated on the contract drawings shall be electric arc welding and shall comply in all respects with the codes and specifications herein noted covering the specifications for design, fabrication, and inspection of welded structures and the qualifications of welders and supervisors. The heat, input, length of weld, and sequence weld and cooling process shall be controlled to prevent distortions. 
.2 For weldments comprised of plates in more than one plane and whose configuration could cause restraint to uniform cooling of the weldment, conform to detailed welding procedures prepared by a welding expert. .
3 For weldments comprised of plates in more than one plane and whose configuration could cause restraint to uniform cooling of the weldment, conform to detailed welding procedures prepared by a welding expert. .
4 For weldments comprised of plates thicker than 40 mm. Take adequate.precaution to control welding and cooling processes in order to control thermal shrinkage stresses. Use stress relieving techniques where necessary. Each welder shall mark his identification symbol on this work. 


Comments

Popular posts from this blog

Differences between development length, anchorage length and splice length

  1-Development length Ld It is the minimum length of a reinforcing bar that must be embedded or "developed" in concrete to ensure that the bar can achieve its full strength in tension or compression. 2-Anchorage length La The distance that the reinforcement extends from the point where the bars are no longer required to resist moments 3-Splice length LS The distance require to transfer the force from bar to another one to upload full presentation please download this  https://drive.google.com/file/d/1layyDvTlJOLzo3jfoW4K5O5UEkgoEzgN/view?usp=sharing

KEYSTONE RETAINING WALL

 Introduction:- Keystone is a mechanical stabilized earth wall MSEW which used to retain soil from one side, it's less cost than concrete walls. Material  1-Keystone Blocks 2-Fiberglass Pins 3-Geo-grids 4- Back-filling Material 5-Concrete pad  Different type of Geogrid:  TT045 can carry load till 45KN/m. TT060 can carry load till. 60KN/m. TT090 can carry load till 90KN/m.  TT120 can carry load till 120KN/m.  TT160 can carry load till. 160KN/m. Method Statement  1) Place HDPE Geogrids on top of the compacted soil. HDPE Geogrids are installed from the front on top of the fiber glass pins (which penetrates the grid) and from to back, Geogrids are fixed horizontally using a steel bars.  2) Lay down the precast concrete units on top of a PC foundation at a level that is a Minimum of 5% from the wall height and reach 10% (buried height) to prevent any lateral movement .  3) Put the layers of Geotextile.  4) Backfilling using fine gravel b...

متي نستخدم اسمنت مقاوم للكبريتات؟

***  عند وجود الخرسانه في بيئه ضاره سواء كانت من المياه أو التربه تتعرض الخرسانه لمهاجمه من الأملاح والاحماض وهذا يضر بالخرسانه. استخدام اسمنت المقاوم للكبريتات والعزل الجيد الخرسانه يكون حل فعال الي حد كبير لحمايه الخرسانه . الجدول المرفق يوضح انواع الأحماض والاملاح التي تؤثر على الخرسانه وطرق الوقايه من تأثيرها الضار . انواع ‏الخوازيق ‏الخرسانيه ‏وطرق ‏تنفيذها