this is some of FIDIC clauses and actions required by contractor and employee Clause no Clause Action by Action 1.9 Delayed drawings Contractor - Give notice to engineer -EOT+ cost+ profit 1.13 Compliance with laws Employer To give all required permits and licenses Contractor For delayed permits : EOT+ cost+ profit 1.6 Contract agreement Employer Within 35 day after letter of acceptance 2.1 Right of access to the site Employer Contractor If delayed EOT+ cost+ profit 2.4 Employers financial arrangement employer Give notice to the contractor when 1-variation >10% or sum of all variations >30% 2- doesn’t receive p...